Current Status:

Drywall: 80% Complete
Wood Flooring Installation: 20% Complete
Millwork Fabrication: 20% Complete
Caulking: 50% Complete
Mechanical ductwork: 90% complete
Plumbing Rough In: 95% Complete
Electrical Rough In: 90% complete

Future Activities (Next 30 Days):

Interior Doors: Begin Installation
Sitework: Begin Courtyard Grading/Piping
Exterior Concrete: Begin Exterior Slabs and Stairs
Cabinetry: Begin Installation
Ceramic Tile: Begin Installation

As the hot summer days wane, we observe with great happiness the construction of the new Priory building. We recently had our site inspection of the exterior brick work. Inside, beginning on the second floor, the wood flooring is being laid, donated by a generous parishioner. We recently received an altar stone for our Priory Chapel – another donation from a generous parishioner. Fr. Scordo heads up the committee for the selection of the interior furnishings. They have been hard at work finding sturdy and simple furniture for the Priory. Fundraising continues. Thanks to the generosity of our parishioners and many donors, we have just over $2 million left to raise.

Comments are closed.