Summer Update

Current Progress:

  • Drywall: 2nd floor complete; 1st floor begun
  • Masonry: 95% complete
  • Mechanical Ductwork: 70% Complete
  • Electrical: 95% complete

Next 30 Days:

  • Roofing: Asphalt Shingle Installation
  • Fire Protection: Begin Sprinkler Installation
  • Landscaping: Preliminary Sketches
  • Furnishings: Initial Selection Process
  • Complete Masonry
  • Complete Roofing
  • Begin Drywall on 1st Floor
  • Install Mechanical Air Handlers

The exterior has truly taken shape; now the friars are making numerous selections for the interior of their new home: Chapel interiors and furnishings, flooring, cabinetry, countertops, desktops, some bookcases, and appliances will all be installed before the end of the year. There is much more to select, and many new and exciting developments to come for the St. Thomas Aquinas Priory!